The Future Homes Standard, introduced through Part L 2026, comes into force on 24 March 2027. Despite the headlines, the minimum fabric U-values, the maximum permitted air permeability and the legal position on gas boilers are unchanged; the real change sits in the notional dwelling, the compliance targets and as-built verification.
Six months until the Future Homes Standard – do not be fooled by the headline minimum requirements. On face value, almost nothing looks dramatically different. That is exactly why developers, architects, housebuilders and M&E consultants risk being caught out.
This is the first article in our Future Homes Standard series. We have written it for the project teams we work with most often across the South of England: residential developments of roughly 10 to 50 units, where compliance decisions made early tend to save time, redesign and cost later.
The short answer is that Part L has become more demanding without looking dramatically different at headline level.
The Building Regulations Part L addresses both the conservation of fuel and power and the minimisation of greenhouse gas emissions. For most teams, the practical consequence is not a sudden new backstop table. It is a tighter and more interdependent compliance exercise.
At Energy Report, this is the sort of issue we spend a lot of time helping project teams work through. Our founder has spent 17 years in building energy compliance, and the recurring pattern is familiar: projects rarely get into trouble because one headline rule was missed. They get into trouble because a familiar-looking standard hides a tougher overall result.
Main commencement dates
The general implementation date for the new regulations is 24 March 2027.
The legislation also provides a separate commencement date of 24 September 2027 for regulations applying to relevant higher-risk building work and work to existing higher-risk buildings.
The one-year transitional grace period
For non-higher-risk work, the 2026 amendments will generally not apply where:
This is the one-year grace period. It is the mechanism that allows some schemes to continue under the previous requirements.
What “commencement” means for a new dwelling
This point is often misread.
For a new dwelling, building work is commenced only when the sub-surface structure, including all foundations, any basement and the ground-floor structure, is completed. Site clearance, enabling works, demolition, or the start of drainage and groundworks do not count.
The trigger is completion of the sub-surface structure and the ground-floor structure. “Commenced” needs to be read as a technical milestone, not as simply being on site.
Why the transitional test is applied per building
The transitional test applies per building, not per site.
That means an early application for one plot, block or phase does not automatically protect an entire development. It is not enough to have an early approval route in place for the wider scheme if the particular building has not met the legal test.
Higher-risk building work follows a separate route
Higher-risk building work follows a separate route.
A valid building control approval application submitted to the regulator before 24 September 2027 may provide transitional protection, subject to the conditions in the regulations, including the application not being rejected.
A practical rule of thumb for developers
This is not the legal test, but it is a useful programme reality check.
If a development of 10 or more homes is not already in planning now (Sept 2026), the likelihood is that it will need to be built under Part L 2026, which introduces the Future Homes Standard. That is based on typical planning, technical design, discharge of conditions, procurement and mobilisation timescales.
For many developers and housebuilders, especially on sites across the South of England, that is the more useful early warning. The legal test still sits in the transitional provisions and must be checked per building.

The clearest way to understand this article is to separate the headlines from the actual regulations.
What the familiar-looking headline standards really mean
Minimum fabric U-values have not changed
There is no dramatic new backstop U-value table that suddenly makes current specifications non-compliant.
That matters because many teams assume a familiar fabric table means familiar compliance. It does not. A dwelling can still become much harder to pass overall even if the headline minimum U-values look the same.
Maximum permitted air permeability has not changed
The maximum permitted air permeability figures in Approved Document L, Volume 1, Table 3.1 remain:
Those are the official figures. They have not tightened at headline level.
The risk is in assuming that an unchanged legal maximum means unchanged practical targets. It does not. Measured performance and the way it feeds into as-built compliance are where many schemes will feel the pressure.
Gas boilers have not been banned
There is no outright prohibition on gas boilers in the regulations.
That is an important distinction. The regulations do not say “no gas boilers from 2027”. In practice, though, achieving compliance with a gas boiler under the new targets is genuinely difficult, which is why heat pumps are likely to be the practical route on most schemes.
Solar PV is effectively required in practice
The most visible new requirement is functional requirement L3.
When a building is erected that is or contains one or more dwellings, a system for on-site renewable electricity generation must be installed on the building or within its curtilage. The system must:
The legal wording is on-site renewable electricity generation. It is not written as “solar PV must be installed in every case”.
In practice, PV is the route most teams will take. Most developments already include PV, so for many project teams this is the least surprising part of the standard.
For dwellinghouses, Approved Document L Volume 1 uses a reference approach based on an annual output equivalent to a photovoltaic array using:
Alternatively, the reasonably practicable roof area may be used with the same panel efficiency.
There are also defined limitations and exemptions. These include cases where a reasonable output cannot be achieved because of the building’s design or surroundings, and cases where equivalent renewable generation is available to residents from another on-site system. Where the standard output cannot be met, the design team must maximise the reasonably practicable output and provide evidence to building control.
Part L now has a wider functional focus
The amended functional requirement ADL1 requires reasonable provision for:
That is a broader and more joined-up requirement than simply selecting efficient products. The design, installation and commissioning of the complete system matter.
The updated Approved Document L, Volume 1: Dwellings remains the key guidance document for project teams.
As-built verification matters more than many teams expect
Every new dwelling should have an air pressure test.
Testing should follow the approved procedure in CIBSE TM23. The measured air permeability must then be used in the as-built energy calculations. Failed dwellings should be improved and retested, and results, including failures, should be reported to the building control body.
That is why airtightness should be treated as a design and construction issue, not a late compliance check. Drawings should identify the air barrier, penetrations should be planned and sealed, and junctions should be reviewed before they are covered up.
Our air tightness testing service supports this stage by helping project teams verify whether the completed dwelling matches the design assumptions.
Thermal bridging still needs active coordination
A good overall U-value does not remove junction heat-loss risk.
Details at ground-floor edges, wall-to-floor junctions, openings, roofs and structural penetrations should be designed, assessed and checked during construction. On schemes with repeated house types, small junction assumptions can have a disproportionate effect.
Our thermal bridging assessments help teams resolve those details before they turn into site issues or SAP shortfalls.
Building services and handover are part of compliance
The updated guidance also covers:
The regulations also introduce regulation 40C, requiring information given to owners of new dwellings to be provided in an appropriate format.
The Approved Document explains that operating and maintenance information should be:
For new dwellings, the Home User Guide should include practical information about heating and hot water, on-site electricity generation, ventilation, and staying cool in hot weather where relevant.
If you are reviewing a scheme now, focus first on timing and scope.
Check which buildings may fall within the new regime. Then test whether any transitional route is realistic on a per-building basis, rather than assuming the whole site is protected.
After that, review the specification as a joined-up compliance package. On the projects we typically support, this usually means coordinating:
For residential developments in the 10 to 50 unit range, these decisions rarely sit in isolation. Roof layout, services strategy, junction design, programme sequencing and evidence for building control all affect the end result.
The Future Homes Standard comes into force on 24 March 2027.
A separate commencement date of 24 September 2027 applies to relevant higher-risk building work and work to existing higher-risk buildings.
For a new dwelling, commencement means the sub-surface structure, including all foundations, any basement and the ground-floor structure, has been completed.
Site clearance, enabling works, demolition, or the start of drainage and groundworks do not count.
No. The minimum fabric U-values have not changed at headline level.
There is no new backstop U-value table that suddenly makes typical current specifications non-compliant.
No. The maximum permitted air permeability has not changed.
The current Approved Document L, Volume 1, Table 3.1 values remain 8.0 m³/(h·m²) at 50 Pa and 1.57 m³/(h·m²) at 4 Pa.
No. Gas boilers are not banned outright.
The issue is practical rather than purely legal: achieving compliance with a gas boiler under the new targets is genuinely difficult, so heat pumps are the more realistic route on most schemes.
Not in those exact words. The legal requirement is for on-site renewable electricity generation, not “solar PV in every case”.
In practice, solar PV is the route most developments will use to satisfy L3, which is why it is effectively required on most schemes.
No. Early applications do not automatically protect an entire site.
The transitional test is applied per building, not per development, so each building must satisfy the relevant conditions in its own right.